Den

Original Condition on Closing Day

Plans - Everything will be replaced - floor, windows, fan, lights, and walls.  The cedar siding won the walls will be removed for reuse on the exterior as the french door will be replaced by a window.  Other doors will also be replaced and will need the siding.  The den walls will be drywall.  Moulding will be replaced and painted white while leaving the doors as natural wood.  Brown electrical units will be replaced with white.






Week 26 - Monday, April 20

Caulked moulding.



Week 25 - Monday, April 13

No significant changes as work was focused in other areas.

Week 24 - Monday, April 6

No significant changes as work was focused in other areas.

Week 23 - Monday, March 30

No significant changes as work was focused in other areas.

Week 22 - Monday, March 23

Installed mouldings.




Week 21 - Monday, March 14

Cut and painted moulding.



Week 20 - Monday, March 9

No significant changes as work was focused in other areas.

Week 19 - Monday, March 2

No significant changes as work was focused in other areas.

Week 18 - Monday, February 24

Floor installation was completed.  Installed ceiling lights.  Finished electrical work.



Week 17 - Monday, February 17

Traced electrical circuit breakers and installed switch/outlet covers.



Week 16 - Monday, February 10

Installed HVAC vent.


Week 15 - Monday, February 3

Painted walls.  Installed door frame.



Week 14 - Monday, January 27

Floors were stained and polyurethane applied.  Started to cut moulding.  Walls were primed.




Week 13 - Monday, January 20

Wood floor installed.  Drywall installation completed.




Week 12 - Monday, January 13

Painted ceiling.  Drywall installation started.  Electrical boxes moved and switches, receptacles replaced with white units.



Week 11 - Monday, January 6

Windows and insulation were installed.  Plywood subfloor was installed.



Week 10 - Monday, December 30

Christmas - no work.

Week 9 - Friday, December 20

No significant changes as work was focused in other areas.

Week 8 - Monday, December 16

No significant changes as work was focused in other areas.

Week 7 - Monday, December 9

Removed siding and window/door mouldings from walls.  Siding removal was a slow process since I wanted to save as much as possible for outside use in the areas where windows would replace doors.  It was very brittle and I managed to save about 1/3.  Nailed subfloor to joists.




Week 6 - Monday, December 2

Due to Thanksgiving travel, no significant changes as work was focused on vendor contacts.

Week 5 - Monday, November 26

Removed subfloor. Cleaned up nails in floor.



Week 4 - Monday, November 19

Removed carpet. Started removal of siding on front wall.


Week 3 - Monday, November 12

No significant changes as work was focused in other areas.

Week 2 - Monday, November 5

No significant changes as work was focused in other areas.

Week 1 - Monday, October 28

Removed shelf and brackets, antenna, speaker wires, and nails









Comments

Popular posts from this blog

Weekly Summary

Week 2 - Monday, November 5

Week 4 - Monday, November 19