Original Condition on Closing Day

Plans - Work will be on the surfaces except that the floor, appliances, and light will be replaced.  The floor will be tiled.  The window will be retained and replaced in the future but will be painted.  The walls and cabinets will be painted.  Moulding will be painted white while leaving the doors as natural wood.






Week 26 - Monday, April 20

No significant changes as work was focused in other areas.

Week 25 - Monday, April 13

Installed door and new hardware.


Week 24 - Monday, April 6

No significant changes as work was focused in other areas.

Week 23 - Monday, March 30

Installed sink.


Week 22 - Monday, March 23

Installed appliances.  Started to install sink.


Week 21 - Monday, March 16

Appliances put in place.  Installed, caulked, and painted mouldings.


Week 20 - Monday, March 9

Finished tiles floors with grout.  Painted door jambs and window frames.  Finished cabinets and temporarily set new sink in place.



Week 19 - Monday, March 2

Finished tiling floor.  Painted cabinet.




Week 18 - Monday, February 24

Installed another new light and started floor tiling.



Week 17 - Monday, February 17

Painted walls and window moulding.  Installed concrete backer board on floor.


Week 16 - Monday, February 10

Removed washer/dryer.  Installed new light and subfloor.  Started to paint window moulding.


Week 15 - Monday, February 3

No significant changes as work was focused in other areas.

Week 14 - Monday, January 27

No significant changes as work was focused in other areas.

Week 13 - Monday, January 20

No significant changes as work was focused in other areas.

Week 12 - Monday, January 13

No significant changes as work was focused in other areas.

Week 11 - Monday, January 6

No significant changes as work was focused in other areas.

Week 10 - Monday, December 30

Christmas - no work.

Week 9 - Friday, December 20

No significant changes as work was focused in other areas.

Week 8 - Monday, December 16

No significant changes as work was focused in other areas.

Week 7 - Monday, December 9

No significant changes as work was focused in other areas.

Week 6 - Monday, December 2

Due to Thanksgiving travel, no significant changes as work was focused on vendor contacts.

Week 5 - Monday, November 26

Removed vinyl floor and subfloor.



Week 4 - Monday, November 19

Removed mouldings.


Week 3 - Monday, November 12

Primed walls.




Week 2 - Monday, November 5

Replaced dryer vent, removed shelves, and repaired walls.



Week 1 - Monday, October 28

Removed curtains, blinds, and hardware.  Removed mullions from windows.  








Comments

Popular posts from this blog

Weekly Summary

Week 2 - Monday, November 5

Week 4 - Monday, November 19