Master Bathroom

Original Condition on Closing Day

Plans - Everything will be replaced - cabinets, floor, lights, and fixtures.  The floors will be tiled.  The shower will be tiled.  The tub will be replaced with a stand-alone tub.  The bidet will be removed and replaced with a small closet.  The wallpaper will be stripped and the molding will be painted white while leaving the doors as natural wood.









Week 26 - Monday, April 20

No significant changes as work was focused in other areas.

Week 25 - Monday, April 13

Contractor installed counter top.  Installed, caulked, and painted wainscoting and moulding,  Installed doors and new hardware.







Week 24 - Monday, April 6

Painted vanity walls.  Installed light.  Repaired walls.






Week 23 - Monday, March 30

Installed drywall.  Installed toilet.  Installed shower walls and repaired ceiling.




Week 22 - Monday, March 23

Repaired walls.  Installed mouldings.  Plumber finished water lines in cabinets.







Week 21 - Monday, March 16

Cut and painted moulding.  Installed cabinet.




Week 20 - Monday, March 9

Finished tiles floors with grout.  Painted door jambs.





Week 19 - Monday, March 2

Finished installation of shower base.  Finished installation of cement backer board and installed tiles on floor.




Week 18 - Monday, February 24

Installed cement backer board on floor.


Week 17 - Monday, February 17

Laid out and cut cement backer board for floor.  Painted window moulding.




Week 16 - Monday, February 10

Plumber installed drain in shower pan.  Started to install subfloor.




Week 15 - Monday, February 3

Removed wall cabinet and started tub-area wall repair.



Week 14 - Monday, January 27

No significant changes as work was focused in other areas.

Week 13 - Monday, January 20

No significant changes as work was focused in other areas.

Week 12 - Monday, January 13

Filled in hole with new joists and subfloor.



Plumber cleaned up sink connections in preparation for cabinet installation and installed shower pipes.



Week 11 - Monday, January 6

No significant changes as work was focused in other areas.

Week 10 - Monday, December 30

Christmas - no work.

Week 9 - Friday, December 20

No significant changes as work was focused in other areas.

Week 8 - Monday, December 16

No significant changes as work was focused in other areas.

Week 7 - Monday, December 9

No significant changes as work was focused in other areas.

Week 6 - Monday, December 2

Due to Thanksgiving travel, no significant changes as work was focused vendor contacts.

Week 5 - Monday, November 26

General cleanup.





Week 4 - Monday, November 19

Removed tile floor and subfloor.  Removed mouldings.  Removed toilet and bidet.



Week 3 - Monday, November 12

No significant changes as work was focused in other areas.

Week 2 - Monday, November 5

Completed the tub removal.  This took 3 full days.  The more I try to take this house apart, the more I discover that it is well built.


This is a picture of the tub partially removed.  It shows that the tile was attached to a layer of concrete that was an inch or more thick.


The platform on the ends and back were tiled.  Below the tile was the 1"+ of concrete, a layer of 3/4" plywood, and 2 layers of 2" wood.  The picture beloe shows the bottom of the plywood.  It resembles a bed of nails.


Completed the shower removal including rewiring the light switch to move it from the shower area.  The shower took 2 full days.


Due to the wet work of wallpaper removal and the electrical work in the bathroom, I have spent several hours mapping portions of the electrical system to the appropriate circuit breaker.

Week 1 - Monday, October 28

Began dissembling the shower by breaking walls to determine water line locations.



Began dissembling the shower by breaking walls to determine water and electric line locations.