Week 3 - Monday, November 12
This week was one of slow progress on the house but lots of progress with vendors as we spent considerable time visiting cabinet places, lighting stores, countertop fabricators, etc. Most of the house work wasn't structural but more getting facades ready for finishing.
Foyer - Original
Foyer - Week 2
Removed chair rail and began
wall repair.
|
Foyer - Week 3
Completed wall repair. Removed chair rail. Primed walls and mouldings. Caulked mouldings.
Foyer - Original
Foyer - Week 3
Completed wall repair. Removed chair rail. Primed walls and mouldings. Caulked mouldings.
Foyer Closet
Foyer Closet - Week 1
Removed wallpaper.
|
Foyer Closet - Week 2
Repaired wall.
|
Foyer Closet - Week 3
Started to prime wall.
Master Bedroom - Original
Master Bedroom - Week 3
Repaired and sanded walls.
Master Bedroom - Original
Master Bedroom - Week 3
Repaired and sanded walls.