Week 1 - Monday, October 28
Photos taken Monday, October 28.
The first week of our renovation work is in the books. Our work schedule looks like it will follow a similar pattern. We will work a full day on Monday, Tuesday, Thursday, and Friday. Wednesday will be "shopping day" where we visit vendors to get bids, buy products, and see options with our own eyes. Saturday is college football day and we will take that day off to rest. Sundays will be light work after church.
My first task was to get all of the stuff off the walls. This includes curtains, blinds, shelves, hangers, etc. It took a full 2 days just to get the walls to a starting point. The parts nearly filled a drawer.
It did make an immediate improvement in the appearance of the rooms.
Foyer Closet - Week 1
Kitchen - Original
Den - Original
Laundry - Original
Master Bedroom - Original
Master Bedroom - Week 1
Master Bathroom - Original
Guest Bathroom - Original
The first week of our renovation work is in the books. Our work schedule looks like it will follow a similar pattern. We will work a full day on Monday, Tuesday, Thursday, and Friday. Wednesday will be "shopping day" where we visit vendors to get bids, buy products, and see options with our own eyes. Saturday is college football day and we will take that day off to rest. Sundays will be light work after church.
My first task was to get all of the stuff off the walls. This includes curtains, blinds, shelves, hangers, etc. It took a full 2 days just to get the walls to a starting point. The parts nearly filled a drawer.
It did make an immediate improvement in the appearance of the rooms.
Foyer Closet - Week 1
Removed wallpaper.
Great Room - Original
Great Room - Week 1
Removed blinds and hardware.
When all the walls were cleaned of hardware, we started on more difficult work. Susan worked on wallpaper removal and I started demolition of the master bathroom. Demo Day!!!
Kitchen - Week 1
Removed curtains, blinds, and hardware. Began wallpaper removal.
Den - Original
Den - Week 1
Removed shelf and brackets, antenna, speaker wires, and nails
Den - Original
Den - Week 1
Removed curtains, blinds, and brackets. Removed mullions from windows.
Den - Original
Den - Week 1
Removed nails and hangers. Removed cables.
Laundry - Original
Laundry - Week 1
Removed curtains, blinds, and hardware. Removed mullions from windows.
Master Bedroom - Original
Removed curtains, blinds, and hardware. Removed saloon doors.
Master Bathroom - Original
Master Bathroom - Week 1
Began dissembling the shower by breaking walls to determine water line locations.
Master Bathroom - Original
Master Bathroom - Week 1
Began dissembling the shower by breaking walls to determine water and electric line locations.
Master Closet (Large) - Original
Master Closet (Large) - Week 1
Removed curtains, shelves, and hardware. Removed mullions from windows. Repaired holes with spackle.
Guest Bedroom - Original
Guest Bedroom - Week 1
Removed curtains, blinds, and hardware.
Guest Bedroom - Original
Guest Bedroom - Week 1
Removed curtains, blinds, and hardware. Removed mullions from windows.
Guest Bathroom - Week 1
Removed curtains and hardware. Removed mullions from windows.